The following is ab Aug. 8, 2022, Government Accountability Office report, Navy Should Provide Congress More Complete Information on Budget Request Decisions.
Why GAO Did This Study
Congressional conferees expressed concern that recent budget requests underfunded critical Navy weapon system programs that were using multiyear procurement authority. They also questioned whether the Navy’s budget requests in recent years for programs using multiyear procurement accurately reflected the service’s most important priorities.
The conferees included a provision for GAO to review certain activities related to Navy multiyear procurements in recent years. This report addresses (1) the extent to which Navy programs fulfilled their multiyear procurement plans in fiscal years 2021 and 2022; and (2) factors contributing to any budget requests for fiscal years 2021 and 2022 that did not include the multiyear procurement quantities stated in the contracts.
To conduct this assessment, GAO reviewed seven programs with active multiyear procurement contracts in fiscal years 2021–2022. GAO also reviewed relevant legislation, policy, and guidance; reviewed budget and contract information; and interviewed Department of Defense officials.
What GAO Recommends
GAO is making one recommendation to the Department of Defense, that it establish a requirement to ensure that the congressional defense committees receive notification of the rationale for any budget requests that do not fund the procurement quantities stated in multiyear contracts. The Department of the Navy concurred with the recommendation.What GAO Found
The Navy used multiyear procurement—a special method to contract for multiple years of requirements in a single contract—for seven critical weapon system programs in fiscal years 2021 and 2022. This contracting method can save the government money through procurement efficiencies but can include future financial commitments. GAO reviewed the seven programs and found that the budget requests for three programs included quantity reductions when compared to their multiyear contracts or previous Navy plans. This hampered their efforts to meet warfighting needs:
Navy officials told GAO that affordability was the primary driver leading to the reduction in quantities requested for DDG 51 and V-22 in the fiscal year 2022 budget. However, GAO found that Department of Defense financial management regulation does not require the Navy to notify the congressional defense committees of its rationale for budget decisions that do not support the procurement quantities stated in multiyear contracts. The lack of such notification can hamper the ability of the committees to oversee programs and make decisions without having to request supplemental information and explanations from the Navy.
The Navy included additional quantities for the DDG 51, V-22, and Virginia class programs in unfunded priorities lists provided to the defense committees. Congress ultimately decided to fund the procurement of additional quantities.