Ground stability works at Ripon Leisure Centre are set to cost £3.5m and cause further delays for a refurbishment project which is already over budget and more than a year overdue.
The costs have been revealed in a Harrogate Borough Council report which said the project now won’t be completed until spring 2024.
The centre’s new swimming pool opened earlier this year, but plans for a larger gym and exercise studios have been delayed after underground voids were discovered beneath the older half of the site which was built in 1995.
Engineering firm Stantec carried out ground investigations over winter and has now proposed remedial works which will cost the council £3.5m and mean parts of the centre are closed for at least ten months from November.
A temporary gym in the venue’s car park has also been proposed and will cost an additional £300,000, while the new swimming pool will remain open throughout.
Ripon’s Jack Laugher Leisure and Wellness Centre
A report to a meeting of the council’s cabinet next week said the authority had made “every effort to provide an accurate estimate” of the costs, but added these could rise further once the ground stability works begin.
The report also said: “It is appropriate and timely to undertake the remedial works now.
“The consulting engineer has previously stated that in their professional opinion a do-nothing approach is unacceptable from a public safety perspective.
“By undertaking the works, which also include installing post works monitoring equipment, the council will ensure that it has put into place adequate mitigation to address the risks.”
A decision to build the new swimming pool next to the existing leisure centre was made in 2019 despite some councillors raising “deep concerns” over ground stability issues at the site where a sinkhole opened up the previous year.
The council continually insisted that professional advice made it clear that the site is “safe to use” before it awarded a £10m contract for the project to construction firm Wilmot Dixon in 2020.
Since then, a further £4.5m has been set aside by the council after the discovery of the underground voids and other issues which delayed the opening of the new swimming pool.
This extra money does not include the ground stability works or temporary gym costs revealed this week.
If approved by cabinet members, the ground stability works will start in December and end next summer before checks are carried out and a monitoring system is installed.
The refurbishment works would then start after this, with completion in spring 2024.
We want our comments to be a lively and valuable part of our community – a place where readers can debate and engage with the most important local issues. The ability to comment on our stories is a privilege, not a right, however, and that privilege may be withdrawn if it is abused or misused.
Please report any comments that break our rules.
This website and associated newspapers adhere to the Independent Press Standards Organisation’s Editors’ Code of Practice. If you have a complaint about the editorial content which relates to inaccuracy or intrusion, then please contact the editor here. If you are dissatisfied with the response provided you can contact IPSO here
© 2001-2022. This site is part of Newsquest’s audited local newspaper network. A Gannett Company. Newsquest Media Group Ltd, Loudwater Mill, Station Road, High Wycombe, Buckinghamshire. HP10 9TY. Registered in England & Wales | 01676637 |
Data returned from the Piano ‘meterActive/meterExpired’ callback event.
As a subscriber, you are shown 80% less display advertising when reading our articles.
Those ads you do see are predominantly from local businesses promoting local services.
These adverts enable local businesses to get in front of their target audience – the local community.
It is important that we continue to promote these adverts as our local businesses need as much support as possible during these challenging times.